Case Study - Amway Brand Centre , Selangor

Project data

  • Customer
  • Amway
  • Value
  • Undisclosed
  • Area
  • 120,000 sq ft
  • Programme duration
  • 33 weeks
  • Completion date
  • August 2010
  • Project Manager
  • CST Asia
  • Quantity Surveyor
  • Northcroft Lim Peruding
  • M&E Engineer
  • Primetech Asia

Overview

Comprising 120,000 sq ft, spread across an office and warehouse building this project involved delivering a massively diverse range of interior accommodation ranging from that associated with corporate office, through to retail, healthcare, hospitality and even industrial to global quality standards. Through the provision of a diverse, focused, “hands on” construction team, ISG was able to deliver unilaterally in all aspects of this project.

Through specialist domestic and nominated contractors, ISG provided a 330 m conveyor system, flow racks, shelving, pick to light system and carton sealer in the warehouse. Through this heavily automated system connected to the main comms room, Amway are able to manage their in house product inventory. The significant integration between five specialist contractors was necessary to deliver this aspect of the works.